As some of you know I am doing some rewiring work.

Currently I have a 200A service coming into the house and the panel is full. An electrician came in a few months back and added a 60A sub panel just so we would have a little breathing room and installed a 220 circuit for my bandsaw and sander.

I am now looking to add a bunch of new circuits and prep a better shop. This includes a 28A Table saw, at some point in the future a 50A wide belt sander (and this doesn't count the compressor and dust collectors needed) a 3-5 hp dust collector, maybe a CNC machine at some point, a large disk sander... etc. etc.

Obviously that 60A sub panel is not going to get me to first base.

Does anyone know how much service there is coming into residential homes? Someone told me that they bring 600A into the house. Does this sound right? Could I realistically have an additional 200A panel added without having to upgrade my electrical service?

And... if electrical service upgrades are needed, what is involved with that, and (ball park) what kind of investment is that?


_________________
Brock Poling
Columbus, Ohio
http://www.polingguitars.com


Top
 Profile  
 
 Post subject:
PostPosted: Sat Oct 13, 2007 1:01 pm 
Offline
Contributing Member
Contributing Member

Joined: Mon Dec 27, 2004 11:25 pm
Posts: 7202
Location: United States
You can replace the 60A sub-panel with a 200A panel. Really all it does is give you more spaces. You won't be running all that stuff at once, and would never max out a full 200 Amps of usage all at once, so it's not a big deal.
You'll probably need to replace the cable between the panels to handle the larger amperage though.

_________________
"I want to know what kind of pickups Vince Gill uses in his Tele, because if I had those, as good of a player as I am, I'm sure I could make it sound like that.
Only badly."


Top
 Profile  
 
 Post subject:
PostPosted: Sat Oct 13, 2007 1:12 pm 
Offline
Contributing Member
Contributing Member
User avatar

Joined: Tue Jan 04, 2005 1:43 am
Posts: 1529
Location: Morral, OH
You can add a 200A sub panel off of your main panel BUT you need to add a 200A breaker in the main panel to feed the sub panel. Then, as Don said, you will need to run a larger cable to supply the sub panel rated for 200A.

_________________
tim...
http://www.mcknightguitars.com


Top
 Profile  
 
 Post subject:
PostPosted: Sat Oct 13, 2007 1:22 pm 
Offline
Old Growth Brazilian Rosewood
Old Growth Brazilian Rosewood
User avatar

Joined: Mon Dec 27, 2004 1:20 pm
Posts: 5915
Location: United States

Do you think I can keep the 60A sub panel I have now (thinking for extra circuits around the house, for when i finally get around to finishing the basement, etc.)

and add a 200A sub panel for the shop?


_________________
Brock Poling
Columbus, Ohio
http://www.polingguitars.com


Top
 Profile  
 
 Post subject:
PostPosted: Sat Oct 13, 2007 2:05 pm 
Offline
Cocobolo
Cocobolo
User avatar

Joined: Sat May 13, 2006 4:05 am
Posts: 337
Location: Reno, Nevada
First name: Michael
Last Name: Hammond
Focus: Build
Status: Amateur
Brock:
Chances are that your existing 200A service will not accept a full 200A breaker for another subpanel, it mechanically won't fit . Most services will only accept a 100A breaker for subpanels. That will be sufficient for your additional machine loads in the shop. You are only going to use one machine at a time unless you plan on hiring employees (!?!?)........naaahh, bad idea!!

_________________
The Biggest Little City, Nevada
www.hammondguitars.com
I love building guitars!


Top
 Profile  
 
 Post subject:
PostPosted: Sat Oct 13, 2007 2:25 pm 
Offline
Koa
Koa

Joined: Tue Jul 04, 2006 3:24 am
Posts: 744
Location: United States
One thing to keep in mind is that you only need lots of power if you plan to run everything at once. I had a very similar problem for my shop but concluded that as long as I could run my air compressor, one major piece of equipment (planer, table, band saw, etc.) and my dust collect that I would be ok for most situations. So far it has never been a problem. It is also important to note that some equipment pulls the most amount of amps at start up. To help my situation I converted most of my large machines to 220V since it cuts the amps in half. This usually just requires changing a few wires and really help.

_________________
Brad
Avon, OH


Top
 Profile  
 
 Post subject:
PostPosted: Sat Oct 13, 2007 4:14 pm 
Offline
Contributing Member
Contributing Member

Joined: Mon Dec 27, 2004 11:25 pm
Posts: 7202
Location: United States
Mike might be correct when he says it may only take another 100A panel. The easiest thing to do is go to your local Agent Orange or Papa Smurf store and ask them what you can add. They usually have knowledgeable people in the electrical departments. If that's the case, you may be able to add 2 100A panels. You might have to re-route a circuit to one of the new panels to create the space though.

_________________
"I want to know what kind of pickups Vince Gill uses in his Tele, because if I had those, as good of a player as I am, I'm sure I could make it sound like that.
Only badly."


Top
 Profile  
 
 Post subject:
PostPosted: Sun Oct 14, 2007 12:01 am 
Offline
Old Growth Brazilian Rosewood
Old Growth Brazilian Rosewood
User avatar

Joined: Mon Dec 27, 2004 1:20 pm
Posts: 5915
Location: United States

yeah, I was thinking about routing a couple of the circuits into the sub panel. To open up some room to put the new sub panel breakers in.

You guys are right though... I won't be running many of these machines @ the same time. Probably just 2. The machine and the dust collector.

_________________
Brock Poling
Columbus, Ohio
http://www.polingguitars.com


Top
 Profile  
 
 Post subject:
PostPosted: Sun Oct 14, 2007 12:52 am 
Offline
Contributing Member
Contributing Member

Joined: Mon Dec 27, 2004 11:25 pm
Posts: 7202
Location: United States
Exactly. A friend of mine is a cabinet maker / Corian fabricator who works out of his substantial basement workshop. He has more tools than I'll ever dream of, and comes nowhere near using up his 200A service all at once. He had a very large panel put in to afford him a lot of circuits for the house and the shop, and that's the real key. You just need more spaces.

_________________
"I want to know what kind of pickups Vince Gill uses in his Tele, because if I had those, as good of a player as I am, I'm sure I could make it sound like that.
Only badly."


Top
 Profile  
 
 Post subject:
PostPosted: Sun Oct 14, 2007 1:00 am 
Offline
Contributing Member
Contributing Member

Joined: Mon Dec 27, 2004 11:25 pm
Posts: 7202
Location: United States
BTW, this past spring I added a 100A sub-panel to my primary 100A service panel, giving me more spaces than I'll ever need.

_________________
"I want to know what kind of pickups Vince Gill uses in his Tele, because if I had those, as good of a player as I am, I'm sure I could make it sound like that.
Only badly."


Top
 Profile  
 
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 10 posts ] 

All times are UTC - 5 hours


Who is online

Users browsing this forum: No registered users and 32 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Jump to:  
Powered by phpBB® Forum Software © phpBB Group
phpBB customization services by 2by2host.com